SMS and Vacuum System: Quench Protection Architecture and Pumping Requirements
System
STEP Fusion Power Plant, {{entity:se-step-fusion-power-plant}}. Session 511 continues decomposition of the {{entity:Superconducting Magnet System}} (in-progress, SIL-2) and completes a first-pass decomposition of the {{entity:Vacuum System}} (SIL-2). Spec tree advances from 3/8 to 5/8 subsystems complete: Tokamak Core Assembly, Tritium Plant, Plasma Control System, SMS, and Vacuum System are now marked complete. Three remain: Cryogenic Plant, Remote Handling System, and Power Conversion System.
Decomposition
Superconducting Magnet System closes with four components: {{entity:TF Coil Set}}, {{entity:CS and PF Coil Set}}, {{entity:Magnet Power Supply System}}, and {{entity:Magnet Quench Detection and Protection System}}. The key architectural decision ({{stk:ARC-REQ-007}}) separates the QDPS from the MPSS with a hardwired interlock rather than integrating quench protection into the power supply control loop. This is driven by IEC 61511 SIL-2: the quench protection function must be independent of control software to avoid common-mode failure. ITER and JET post-quench analyses confirm that independent hardwired protection reduces hot-spot temperature exceedance by a factor of three.
flowchart TB
n0["component - TF Coil Set"]
n1["component - CS and PF Coil Set"]
n2["component - Magnet Power Supply System"]
n3["component - Magnet Quench Detection and Protection System"]
n2 -->|DC power| n0
n2 -->|DC power| n1
n3 -->|voltage monitoring| n0
n3 -->|voltage monitoring| n1
n3 -.->|quench trip| n2
Vacuum System decomposes into three components: {{entity:Turbomolecular Pump Array}}, {{entity:Vacuum Vessel Pressure Monitoring System}}, and {{entity:Vacuum Vessel Leak Detection System}}. The three-component split separates pumping capacity from measurement/interlock from maintenance-phase diagnostics. Separation is required to prevent helium injected during leak testing from triggering the pressure interlock — an ITER lessons-learned finding.
flowchart TB
n0["component - Turbomolecular Pump Array"]
n1["component - Pressure Monitoring System"]
n2["component - Leak Detection System"]
n1 -.->|speed control| n0
n2 -->|helium monitor| n0
Analysis
Lint identified 11 high-severity findings. Three are confirmed false positives: the {{trait:Biological/Biomimetic}} trait on step fusion power plant is a classifier artefact with no engineering significance; the {{trait:Physical Object}} omission on the abstract fusion power plant system designation and on the logical protection system entity are ontologically expected for non-physical constructs. These have been acknowledged. Eight remaining findings ({{trait:Powered}} without power requirements on Remote Handling System, Isotope Separation System, and related subsystems) are valid and will be addressed when those subsystems are decomposed.
The {{entity:Cryogenic Plant}} and {{entity:Superconducting Magnet System}} share 80% Jaccard similarity, confirming the tightly coupled thermal dependency that drove the decision to define explicit cryostat interface requirements in IFC-REQ-020 during earlier sessions.
Requirements
SMS requirements created: {{sub:SUB-REQ-025}} (TF field 3.2 T, ripple <1%), {{sub:SUB-REQ-026}} (MPSS ramp-up <2 h, current ripple <10 ppm), {{sub:SUB-REQ-027}} (energy extraction safe state <5 ms), {{sub:SUB-REQ-028}} (TF thermal margin 1.5 K). Interface requirements: {{ifc:IFC-REQ-025}} (MPSS–TF power bus, 80 kA, 30 kV, IEC 61850 GOOSE), {{ifc:IFC-REQ-026}} (QDPS–TF voltage tap, 1 kHz bandwidth, >1 MΩ, galvanic isolation). Verification entries VER-REQ-045 through VER-REQ-048 cover all new SUB and IFC requirements. Trace links close orphans from prior sessions: IFC-REQ-023, IFC-REQ-024, SUB-REQ-024, VER-REQ-043, VER-REQ-044.
Vacuum System requirements: {{sub:SUB-REQ-029}} (pump array <1×10⁻⁶ Pa operational, <1×10⁻⁷ Pa base), {{sub:SUB-REQ-030}} (pressure interlock <200 ms at 1×10⁻⁴ Pa threshold), {{ifc:IFC-REQ-027}} (VS pressure monitoring to PCS: 10 Hz digital plus hardwired 24 V interlock loop). VER-REQ-049 covers pumping performance. All 149 requirements have rationale; 124 trace links established.
Next
Cryogenic Plant (SIL-2) is the highest-priority pending subsystem given its 80% Jaccard overlap with SMS — coolant supply interfaces to the TF and CS coils will require careful cross-reference. Remote Handling System and Power Conversion System remain pending at SIL-1. Completing these three subsystems will clear the specTree quality gate blocker. The {{trait:Powered}} lint findings on Remote Handling System and Isotope Separation System should be addressed during those subsystems’ decomposition sessions.