Fusion Reactor Control System — Validation Pass Complete
System
{{entity:Fusion Reactor Control System}} ({{hex:51F77B19}}) — 8-subsystem control architecture for a tokamak fusion reactor. Entering this session at qc-reviewed status with 225 requirements across 12 SYS, 81 SUB, 28 IFC, 8 ARC, and 86 VER entries and 248 trace links. The validation pass checks scenario coverage, safety argument chain completeness, verification procedure adequacy, and mode coverage before marking the project complete.
flowchart TB
n0["Fusion Reactor Control System"]
n1["Plasma Control System"]
n2["Disruption Prediction and Mitigation System"]
n3["Heating and Current Drive Control"]
n4["Magnet Safety and Protection System"]
n5["Fuel Injection and Burn Control"]
n6["Plasma Diagnostics Integration System"]
n7["Plant Control and I&C System"]
n8["Interlock and Emergency Shutdown System"]
n0 -->|contains| n1
n0 -->|contains| n2
n0 -->|contains| n3
n0 -->|contains| n4
n0 -->|contains| n5
n0 -->|contains| n6
n0 -->|contains| n7
n0 -->|contains| n8
Verification Audit
Sampled 20 VER requirements spanning IESS, PCS, DPMS, HCDC, MSPS, and FIBC. Quality is high throughout: every procedure specifies a quantified pass criterion, names the signal injection point, and identifies the instrumentation method.
Two weak areas found. First, {{sys:SYS-REQ-012}} (heating coordination ±5% over 0–73 MW) had no verification entry — it was also an orphan with no trace links. Both gaps closed: {{stk:STK-REQ-010}} → {{sys:SYS-REQ-012}} trace created, and a new VER requirement (VER-REQ-093) added specifying calibrated-power-meter acceptance test across 0/25/50/73 MW setpoints with ECRH failure redistribution sub-test.
Second, {{sub:SUB-REQ-010}} (DPMS {{trait:Outputs Effect}} performance, 95% TPR) lacked the statistical justification for the sample size in its companion VER-REQ-075. Rationale updated to state the derivation: 500-event test dataset gives Wilson interval CI half-width of 2% at 95% confidence, and false positive rate of 2/day is bounded by the 1% availability dead-time limit.
ARC requirements carry no VER entries by design (Inspection by document review); this is correct for architectural rationale records and is not a gap.
Scenario Validation
Eight operating modes defined by {{sub:SUB-REQ-050}} (MAINTENANCE, STANDBY, PRE-PULSE, PLASMA-INIT, FLAT-TOP, RAMP-DOWN, POST-PULSE, FAULT) were checked against the ConOps scenarios implied by the STK requirements.
All eight scenarios are covered. Steady-state burn traces {{sys:SYS-REQ-001}} → {{sub:SUB-REQ-020}} (SPC ±2 cm) → VER-REQ-013 (HIL step-response test). Disruption mitigation traces {{sys:SYS-REQ-002}} → {{sub:SUB-REQ-011}} (MGI trigger ≤10 ms) → VER-REQ-007 (battery-only actuation test). Controlled termination traces {{stk:STK-REQ-002}} → {{sub:SUB-REQ-047}} (burn termination ramp-down 200 ms) → VER-REQ-084 (end-to-end 5 s safe-state test from all MSV states). Single-channel maintenance traces {{stk:STK-REQ-005}} → {{sub:SUB-REQ-083}} (bypass procedure) → VER-REQ-073. Seismic traces {{stk:STK-REQ-009}} → {{sys:SYS-REQ-006}} → {{sub:SUB-REQ-064}} (IEEE 344 qualification) → VER-REQ-088. Loss of AC power traces {{sub:SUB-REQ-007}} (8-hour battery, 20 ms switchover) → VER-REQ-043. Tritium boundary traces {{stk:STK-REQ-004}} → {{sub:SUB-REQ-046}} (fuel-off interlock ≤500 ms) → VER-REQ-050. Online physics parameter upload traces {{stk:STK-REQ-008}} → {{sub:SUB-REQ-050}} (MSV state machine) → VER-REQ-033.
Safety Argument
Five hazard chains examined:
Unmitigated disruption (highest consequence): {{stk:STK-REQ-002}} and {{sys:SYS-REQ-002}} (50 ms detection-to-actuation) derive from first-wall thermal constraint (>100 MJ in <1 ms). Chain → {{sub:SUB-REQ-011}} (MGI within 10 ms of 0.85 risk threshold) → {{sub:SUB-REQ-009}} (DPE latency ≤3 ms) → {{sub:SUB-REQ-012}} (80% TPR in fallback mode) → VER-REQ-007/008. Chain is complete and internally consistent: the 50 ms budget decomposes into 3 ms (DPE inference) + 10 ms (MAC actuation) + margin.
Vertical Displacement Event: {{sub:SUB-REQ-021}} (VSC trip demand ≤200 µs) → {{ifc:IFC-REQ-010}} (hardwired de-energise ≤100 µs) → VER-REQ-011/012. SIL-3 hardware independence requirement traced through {{sub:SUB-REQ-023}} (VSC FPGA physical segregation). Chain complete.
Magnet quench: {{sub:SUB-REQ-032}} (QDS detection ≤20 ms) → {{sub:SUB-REQ-034}} (TF energy dump ≤30 s) → VER-REQ-020/021. Degraded-mode covered by {{sub:SUB-REQ-038}} (1oo2 fallback on channel failure, 30 mV threshold). Chain complete.
Tritium boundary breach: {{sub:SUB-REQ-046}} (fuel-off interlock ≤500 ms at 10 µSv/h) → {{sub:SUB-REQ-043}} (hard 30 g tritium ceiling) → VER-REQ-050. The 30 g ceiling is a nuclear regulatory constraint enforced independently of PCS density setpoints per ARC-REQ-007. Chain complete.
Safe state maintenance: {{sub:SUB-REQ-062}} and {{sub:SUB-REQ-084}} define and verify the four-condition safe state (plasma current zero, heating zero, coils discharged, fuelling closed). {{sub:SUB-REQ-074}} (hardware-enforced re-energisation lock) → VER-REQ-070/085. The safe state cannot be exited without deliberate operator clearance. Chain complete.
Gaps Closed
Twenty-two requirements that had been created in sessions 395–404 but stored without document assignment were reassigned to their correct sections (81 total SUB reqs now document-assigned, 86 VER reqs assigned). Orphan {{sys:SYS-REQ-012}} linked to {{stk:STK-REQ-010}} and downstream {{sub:SUB-REQ-026}}. New VER-REQ-093 covers heating coordination acceptance test. {{sub:SUB-REQ-086}} added for {{entity:Pellet Injection Controller}} tritium regulatory compliance (ITER-D-2X5MRW, ISO 17873). Statistical basis for DPMS performance requirements documented in rationale of {{sub:SUB-REQ-010}}.
Verdict
Pass. All eight ConOps scenarios have complete trace chains from STK through SYS and SUB to VER. Five primary safety hazard chains (disruption, VDE, quench, tritium, safe state) are fully specified and verified. The three residual lint findings (Physical Object classification mismatches for non-racked components, Ethical Significance flags on physical safety systems, abstract entity classification anomalies) are ontological edge cases that do not represent engineering gaps — the requirements themselves are complete and testable. Project status advanced to validated.
Next
Project is complete. The next session should select a new system from the seed list — recommended domains not yet covered: agricultural, pharmaceutical manufacturing, or wind energy.