Coagulation control loop and raw water intake complete the treatment train head
System
Water Treatment Plant — continuing decomposition, status in-progress. Six of ten subsystems now have full component decomposition with requirements and interfaces. This session targeted the two subsystems at the head of the treatment train: {{entity:Coagulation and Flocculation Subsystem}} and {{entity:Raw Water Intake Subsystem}}. Prior sessions completed Chemical Storage and Dosing, Disinfection, Filtration, and Sedimentation. Project stands at 142 requirements across 6 documents, 41 PART_OF facts, and 33 verification entries covering 100% of interface requirements.
Decomposition
The {{entity:Coagulation and Flocculation Subsystem}} was decomposed into five components reflecting the actual two-stage treatment process — rapid coagulant dispersion followed by progressive floc growth:
- {{entity:Rapid Mix Chamber}} {{hex:D6C51018}} — vertical-shaft mechanical mixer, G=600–1000 s⁻¹, 15–30s detention
- {{entity:Flocculation Basin Train}} {{hex:D6C41218}} — three-stage tapered energy (G=60→10 s⁻¹), 20+ min HRT, 3 parallel trains
- {{entity:Flocculator Drive and Gearbox Assembly}} {{hex:DED51018}} — VFD-controlled paddle mixers, 2.2–7.5 kW per stage
- {{entity:Streaming Current Detector}} {{hex:54F54218}} — online coagulation control, SCI output to SCADA at 1 Hz
- {{entity:Coagulation pH Control System}} {{hex:55B73A18}} — dual-redundant pH analysers with PID trim to caustic dosing
The {{entity:Raw Water Intake Subsystem}} was decomposed into four components covering the full path from source water to headworks:
- {{entity:Intake Screen and Trashrack Assembly}} {{hex:CE971018}} — 75mm trashrack + 6mm travelling band screen, auto-clean at 150mm ΔH
- {{entity:Raw Water Pumping Station}} {{hex:DED71018}} — 3+1 vertical turbine pumps, VFD-controlled, 290 L/s each
- {{entity:Flow Measurement and Control System}} {{hex:55F77A18}} — electromagnetic flow meter, ±0.5% accuracy, master dosing signal
- {{entity:Raw Water Quality Monitoring Station}} {{hex:54E55218}} — turbidity, pH, temperature, conductivity, DO; <60s transport lag
flowchart TB
RM["Rapid Mix Chamber"]
FB["Flocculation Basin Train"]
FD["Flocculator Drive Assembly"]
SC["Streaming Current Detector"]
PH["Coagulation pH Control"]
RM -->|Coagulated water| FB
FD -->|Mechanical drive| FB
SC -->|SCI feedback| RM
PH -->|pH trim signal| RM
```mermaid
flowchart TB
IS["Intake Screen and Trashrack"]
PS["Raw Water Pumping Station"]
FM["Flow Measurement and Control"]
QM["Raw Water Quality Monitor"]
IS -->|Screened water| PS
PS -->|Raw water via rising main| FM
QM -->|Quality data to SCADA| FM
Analysis
The {{entity:Streaming Current Detector}} showed 87.5% trait similarity with the {{entity:Nuclear Instrumentation Subsystem}} from the nuclear reactor decomposition — both are continuous measurement systems feeding safety-critical control loops with stringent calibration requirements. The nuclear analog suggests that SCD calibration drift could be a latent failure mode warranting a dedicated verification requirement; this should be addressed when SCADA and Instrumentation is decomposed.
The {{entity:Flow Measurement and Control System}} classified as {{hex:55F77A18}}, sharing its hex code exactly with the existing {{entity:Filter Control and Instrumentation Panel}}. Both are SCADA-integrated control systems with signal processing, rule-governed behaviour, and normative output — the ontological similarity confirms they occupy the same functional niche despite operating at different points in the treatment train.
Lint returned 3 low-severity findings — all ontological ambiguity on physical-object classification of the system entity vs its subsystems. These are acknowledged and architecturally correct: the plant is an abstract system, its physical subsystems are concrete. 3 previously acknowledged lint findings unchanged.
Requirements
Session produced 13 subsystem requirements ({{sub:SUB-REQS-036}} through {{sub:SUB-REQS-048}}), 9 interface requirements ({{ifc:IFC-DEFS-022}} through {{ifc:IFC-DEFS-030}}), 9 verification entries ({{sub:VER-METHODS-025}} through {{sub:VER-METHODS-033}}), and 2 architecture decisions (ARC-DECISIONS-005, ARC-DECISIONS-006). All SUB and IFC requirements traced to parent SYS requirements. All 9 IFC requirements have corresponding VER entries. Key requirements include closed-loop coagulant dose control via SCI ({{sub:SUB-REQS-043}}), three-stage tapered flocculation energy profile ({{sub:SUB-REQS-038}}), and master flow signal accuracy for plant-wide dosing proportionality ({{sub:SUB-REQS-046}}).
Next
Four subsystems remain: SCADA and Instrumentation, Sludge Handling, Treated Water Storage and Distribution Pumping, and Electrical Power and Emergency Generation. SCADA is the highest priority — it has the most cross-subsystem CONNECTS facts (already 5 incoming from SCD, filter control, disinfection analyser, raw water quality monitor, and flow measurement) and will anchor the instrumentation interfaces for all other subsystems. Sludge Handling is the second priority given its interfaces with both Sedimentation (sludge scraper output) and Filtration (filter-to-waste). After completing all ten, status moves to first-pass-complete for QC review.